FUSO 4M4 – HYBRID ELECTRIC VEHICLE SYSTEM – HIGH VOLTAGE COOLING SYSTEM

Work before installation

Draining of coolant
• Perform draining of coolant in the high voltage cooling system.
(See “ON-VEHICLE INSPECTION AND ADJUSTMENT”.)

Installation procedure

• Installation: Water hose
– Connect the water hose with the pipe fixing the hose end at the spool center or white paint center. (If the hose is properly connected, the measurement indicated in the illustration is 30 ± 3 mm.)
– If the pipe has no white paint, install the water hose so that the measurement indicated in the illustration becomes 30 ± 3 mm.

Work after installation

Refilling of coolant
• After installing the devices and pipes of the high voltage cooling system, refill coolant. (See “ON-VEHICLE INSPECTION AND ADJUSTMENT”.)